News & Insights
The commercial record.
Commentary and analysis on Security of Payment, delay and EOT claims, variations, quantum, and the commercial mechanics of Australian construction.
Article · 31 Aug 2026 · 6 min
Concurrent Delay: Who Bears the Cost When Two Delays Collide
When a principal-risk delay and a contractor-risk delay overlap, who pays? Australia has no apex authority, the SCL Protocol calls true concurrency rare, and the practical default is time-not-money. What the cases actually say, what AS 4000 does about it, and the records that decide it.
Read →Article · 26 Aug 2026 · 5 min
Choosing a Delay Analysis Method: A Practical Guide to the SCL Protocol Options in Australia
The SCL Protocol lists six delay analysis methods; Australian courts have made clear none has automatic standing. The real selection criteria — records, timing, forum and the question being asked — plus the lessons of White Constructions and Santos v Fluor on what survives scrutiny.
Read →Article · 24 Aug 2026 · 6 min
The Prevention Principle and 'Time at Large': What They Actually Mean in Australia
Contractors invoke the prevention principle whenever the principal causes delay; it rarely rescues them. The Australian position: an unused EOT mechanism defeats the argument, Gaymark is an outlier, and clear words can exclude the principle altogether. What 'time at large' really means — and costs.
Read →Article · 19 Aug 2026 · 6 min
Extension of Time Under AS 4000: Getting Clause 34 Right
AS 4000's clause 34 is the most administered EOT regime in Australian contracting and one of the most misunderstood: the cl 34.2 notice and cl 34.3 claim are different obligations, the superintendent has 28 days before a deemed EOT arises, and amendments change everything. A working guide.
Read →Article · 17 Aug 2026 · 6 min
Victoria's Security of Payment Reset: What the April 2026 Reforms Mean for Your Next Claim
From 15 April 2026, Victoria's security of payment regime was rebuilt: excluded amounts and claimable variations abolished, monthly claim entitlement, a 20-business-day payment cap, unfair time bars declarable under s 13A, and a statutory performance security regime — applying to existing contracts.
Read →Article · 12 Aug 2026 · 7 min
Security of Payment Across Australia: NSW, Queensland, Victoria and WA Compared
Every state promises 'pay now, argue later' — then implements it differently. Payment claim timing, schedule deadlines, due-date caps, adjudication windows and the December pauses for NSW, Queensland, Victoria and WA, compared in one place for teams working across borders.
Read →Article · 10 Aug 2026 · 6 min
Adjudication Under NSW SOPA, Step by Step: From Payment Claim to Determination
The three s 17 pathways and their exact deadlines, the s 17(2) notice trap, what goes in the application, the respondent's response window, determination and enforcement — the complete NSW adjudication sequence with the business-day rules that decide it.
Read →Article · 5 Aug 2026 · 5 min
How to Respond to a Payment Claim in NSW: The Payment Schedule Is Your Recovery Roadmap
A payment schedule is not just a number — it is the roadmap for the dispute that may follow. The NSW requirements, the 24–48 hour triage that should happen on receipt of every claim, a six-category framework for deductions, and the s 20(2B) rule that locks in your reasons.
Read →Article · 3 Aug 2026 · 6 min
What Makes a Payment Claim Valid Under NSW SOPA: A Practitioner's Checklist
Identification of the work, the claimed amount, the 'made under the Act' statement, timing, the one-claim-per-month rule, the supporting statement: the validity elements of a NSW payment claim, the traps that kill claims before the merits, and how to audit yours before serving.
Read →Case study · 29 Jul 2026 · 5 min
Taringa v Kenik: When Courts Will Stay an Adjudication Award Over Claimant Insolvency Risk
In Taringa Property Group v Kenik [2024] QSC 327, Queensland stayed enforcement of a $4.2M adjudication award because the claimant's finances made repayment unlikely — the first such stay against a claimant not in liquidation. The builder was wound up weeks later. A playbook for both sides.
Read →Case study · 27 Jul 2026 · 5 min
CMA Assets v John Holland: The Harsh Time-Bar Decision Commercial Teams Should Re-Read Annually
In CMA Assets v John Holland [No 6] [2015] WASC 217, a subcontractor's delay claims failed for non-compliant notices even though the court found the head contractor caused delay — and the clause excluding the prevention principle was upheld. The defining Australian lesson in notice discipline.
Read →Case study · 22 Jul 2026 · 5 min
Southern Han: The Reference Date Rule Every Payment Claim Still Lives By
Southern Han v Lewence [2016] HCA 52 held that a reference date is a precondition to a valid NSW payment claim — and termination can stop new ones arising. The 2019 amendments reversed parts of it for newer contracts, but the validity discipline it teaches still decides adjudications.
Read →Case study · 20 Jul 2026 · 5 min
Mann v Paterson: The High Court Reins In Quantum Meruit
In Mann v Paterson Constructions [2019] HCA 32, the High Court ended the 'generous quantum meruit' after repudiation: no restitution for completed stages, and the contract price effectively caps the rest. What it means for valuing terminated work and documenting variations.
Read →Case study · 15 Jul 2026 · 5 min
White Constructions v PBS Holdings: The Day the Court Rejected Both Delay Experts
In White Constructions v PBS Holdings [2019] NSWSC 1166, the court rejected both parties' delay analyses — windows and collapsed as-built alike — and decided causation on the site records. Still the most important Australian delay-methodology decision, and the reason your site diary matters.
Read →Case study · 13 Jul 2026 · 5 min
A-Civil v Ceerose: When the Adjudicator Goes Off-Script
In A-Civil v Ceerose [2024] NSWCA 7, an adjudicator decided a $115K retention claim on reasoning neither party advanced. The NSWCA upheld the partial setting aside for denial of procedural fairness — a rare successful challenge with lessons for adjudicators, claimants and respondents alike.
Read →Case study · 1 Jul 2026 · 5 min
Kwik Flo: No Second Bite at Adjudication
In Kwik Flo v SE Ware Street Dev [2026] NSWCA 9, a claimant who lost on jurisdiction before one adjudicator obtained $1.2M from a second. The Court of Appeal held the first ruling was a 'determination' and the re-run an abuse of process. The remedy is judicial review — not forum shopping.
Read →Case study · 29 Jun 2026 · 5 min
Rimfire Energy: 865 Days of EOT Lost to Defective Notices
In Rimfire Energy v BSF Co (No 2) [2025] FCA 384, six extension-of-time claims totalling 865 days all failed: none addressed the requirement that the delay wasn't caused by the claiming party. The result was full delay damages. A precise lesson in notice content for every EOT regime.
Read →Case study · 24 Jun 2026 · 5 min
Carbone v Fowler Homes: Why '$1 a Day' Liquidated Damages Don't Cap Your Delay Liability
In Carbone v Fowler Homes [2024] NSWCA 192, a builder argued nominal liquidated damages were the owner's entire remedy for 21 months of delay. The Court of Appeal disagreed: without clear words, a token LD rate leaves general damages at large. The drafting lesson cuts both ways.
Read →Case study · 22 Jun 2026 · 5 min
Santos v Fluor: $692M and a Masterclass in How Courts Test Delay Analysis
Santos v Fluor [2025] QSC 184 adopted a three-referee report and ordered roughly $692M paid on the GLNG cost-reimbursable dispute. Inside it: the standard for adopting referee reports, and a sharp lesson in delay-analysis method discipline. An appeal is pending.
Read →Case study · 17 Jun 2026 · 5 min
Cessnock in the High Court: Recovering Wasted Expenditure When Expectation Loss Can't Be Proved
In Cessnock City Council v 123 259 932 Pty Ltd [2024] HCA 17, the High Court allowed a company to recover $3.7M spent building an airport hangar after the council repudiated. The 'fair wind' principle for wasted expenditure matters to every terminated construction project.
Read →Case study · 15 Jun 2026 · 5 min
EnerMech v Acciona: Clawing Back a Called Bank Guarantee Through SOPA
In EnerMech v Acciona [2024] NSWCA 162, a subcontractor used a SOPA payment claim to recover $9.2M in cashed bank guarantee proceeds — and the Court of Appeal upheld it. Calling security no longer guarantees holding the cash. What both sides of the recourse decision need to know.
Read →Case study · 10 Jun 2026 · 5 min
Roberts Co v Sharvain: The $3.2M Deeming Clause That Couldn't Stop the SOPA Clock
In Roberts Co v Sharvain Facades [2025] NSWCA 161, a head contractor's payment schedule was three days late because it relied on a contractual deemed-service clause. The NSW Court of Appeal confirmed the SOPA clock runs from actual service. The cost: judgment for the full $3.2M claim.
Read →Case study · 8 Jun 2026 · 5 min
Tesseract: Proportionate Liability Now Follows You Into Arbitration
In Tesseract International v Pascale Construction [2024] HCA 24, the High Court held proportionate liability statutes apply in domestic commercial arbitration. Claimants can now be left chasing absent wrongdoers in court; respondents gain a powerful defence. Arbitration clauses need rereading.
Read →Case study · 3 Jun 2026 · 6 min
Pafburn in the High Court: The Non-Delegable Duty That Reshaped NSW Defect Claims
In Pafburn v The Owners – Strata Plan No 84674 [2024] HCA 49, the High Court held that the statutory duty of care under the NSW Design and Building Practitioners Act cannot be apportioned away. What that means for developers, head contractors and their subcontract chains.
Read →Article · 1 Jun 2026 · 8 min
Time Bars and Condition-Precedent Notices: Why Courts Enforce Them and How Not to Lose Your Claim
A valid claim served one day late can be worth nothing. Australian courts consistently enforce time bars and condition-precedent notices as written. Here is why they do it, where the narrow escape routes lie, and the notice discipline that keeps entitlement alive.
Read →The record, delivered
The analysis, before you need it.
Commentary on Security of Payment, delay, variations and quantum — direct to your inbox as it's published. Unsubscribe any time.