InsightsGuidancePublished Last reviewed 6 minute read
Approving in-scope work as a variation does not make it one
In Kaloriziko v Calibre (No 2) [2025] NSWCA 259 the Court of Appeal held that approval could not turn in-scope work into a variation. Entitlement still starts with a written direction, and valuation follows the contract's order of precedence.
By Malachy Mullin, Director
Key takeaways
- 01Kaloriziko v Calibre[2025] NSWCA 259: approving in-scope work as a variation does not make it one, and payments “on account” can be corrected at final account. Record why each item is a variation.
- 02The direction (written, or oral and confirmed fast) is the foundation of variation entitlement; the rescue doctrines (Liebe v Molloy, Update Constructions) are last resorts.
- 03The variations power has limits: no transformation of the project (Wegan), no omitting work to hand it to others (Reed & Stuart).
- 04Valuation follows the cl 36.4 hierarchy; agree prices before performance wherever possible.
Who needs to know: Commercial managers, contract administrators, quantity surveyors and project directors who direct, price, approve or claim variations, for principals, head contractors and subcontractors.
Context
Variations are among the most contested heads of claim on Australian projects, and no area relies more heavily on assumptions that the case law keeps disturbing. The latest disturbance came in December 2025. In Kaloriziko Pty Ltd as trustee for Ryde Combined Unit Trust v Calibre Construction Group Pty Ltd (No 2) [2025] NSWCA 259, the Court of Appeal held that items a developer had approved as variations were not variations, because the work was already within the contract scope. Approval could not turn in-scope work into a variation (at [118]). If your register shows “approved” next to an item, that word proves less than you think.
Entitlement starts with a written direction
Under the standard machinery (AS 4000's clause 36 is the archetype), the superintendent directs variations (additions, omissions, changes in character or quality), and the contractor must not vary the work without a written direction. Three recurrent entitlement problems sit around that simple structure: oral directions, scope and notice.
Work done on an oral direction is recoverable, but only the hard way
Work directed orally and performed sits outside the formal machinery, but it is not unrecoverable. The High Court's Liebe v Molloy (1906) 4 CLR 347 line holds that where the owner knows extra work is being performed, knows it is outside the contract, and knows the builder expects payment, a promise to pay can be implied despite a writing clause. Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251 suggested that recovery of the Liebe kind may now rest on restitution rather than implied contract, but only for work truly outside the contract. Its actual result turned on estoppel: an owner whose agent led the builder to proceed without the contractual notices could not rely on them.
These are rescue doctrines, though: expensive, uncertain and fact-hungry. The operational answer is the contract's own tool. Under AS 4000, a contractor can require written confirmation of an oral direction (cl 20); the standing site rule should be confirmation of every oral instruction within 24 hours.
Whether work is extra at all is a question of construction
Whether work is “extra” at all is a construction question the records must answer: drawings, specification, the contractual design obligations (acute on design and construct contracts, where design development is usually the contractor's risk). And the variations power has outer limits in both directions: it is not a power to transform the project into something manifestly different (Wegan Constructions Pty Ltd v Wodonga Sewerage Authority [1978] VR 67), nor a power to omit work in order to hand it to another contractor (Commissioner for Main Roads v Reed & Stuart Pty Ltd (1974) 131 CLR 378).
Variation claims increasingly carry time bars
Variation entitlement increasingly arrives wrapped in time bars: claims to be notified under the general claims clause within fixed periods. Everything we have written about notice discipline applies here with full force.
Valuation follows a fixed order of precedence
AS 4000 cl 36.4 prices variations in a fixed order: prior agreement; applicable contract rates; rates in a priced bill or schedule to the extent reasonable; and finally reasonable rates and prices including a reasonable amount for profit and overheads. The discipline the order implies (agree the price before the work where possible) remains the single most valuable variation habit on either side of the contract.
- 01
Is the work outside the contract scope?
If not, it is not a variation, whatever was approved (Kaloriziko (No 2) at [107], [118]).
- 02
Was it directed in writing?
The superintendent directs variations in writing (cl 36.1). If a direction is given orally, the contractor can ask for written confirmation (cl 20).
- 03
Price it in the contract's order
(a) Prior agreement; (b) applicable contract rates; (c) rates in a priced bill or schedule, to the extent reasonable; (d) reasonable rates and prices, including a reasonable amount for profit and overheads (cl 36.4).
- 04
Payments before final payment are on account
Under cl 37.2, so an amount approved for in-scope work can be corrected at final account (Kaloriziko (No 2) at [118], [119]).
Fig. 1The first question is whether the work is outside the contract scope. Approval or pricing cannot answer it, and amounts paid on account can be corrected at final account.
Clause numbers are those of AS 4000-1997; other standard forms and amended contracts differ. The steps are the order of questions to ask, not a contractual timetable.
Source: Kaloriziko (No 2) [2025] NSWCA 259 at [107], [118], [119]; AS 4000-1997 cls 20, 36.1, 36.4, 37.2.
Approving in-scope work as a variation does not make it one
At first instance (Calibre Construction Group Pty Ltd v Kaloriziko Pty Ltd (No 2)[2025] NSWSC 593), the builder kept the amounts, because the developer had priced and paid them under cl 36.4 (at [97]). The contract was an amended AS 4902-2000 form, but its cl 36.4 and cl 37.2 work the same way as AS 4000's. The Court of Appeal disagreed on the principle. Approving or pricing a non-variation does not make it a variation, and cl 36.4 is a pricing mechanism that assumes a real variation (at [118]). Because payments before final payment were “on account” (cl 37.2), the developer was entitled to a $133,175 credit for a consultancy-fee item that had been approved, though not yet paid (at [114], [118] to [120]). The builder kept the paid items (variations 1, 7, 11, 13 and 21) only because the contract made services and infrastructure work separately payable (at [108] to [113]). Where cl 36 is followed and a real variation is priced, the builder's right to payment stands (at [119]).
| Item | Status | Scope | Result on appeal |
|---|---|---|---|
| Variations 1, 7, 11, 13 and 21 | Priced and paid by the developer | Within the contract work, but services and infrastructure work the contract made separately payable | Builder kept the amounts (at [108] to [113]) |
| Variation 44 (consultancy fees) | Approved, not paid | Within the contract work and covered by the contract sum | $133,175 credit to the developer (at [114] to [120]) |
Source: Kaloriziko (No 2) [2025] NSWCA 259 at [97], [108] to [114], [118] to [120]; orders of 5 December 2025, order 3(a).
Common pitfalls
- 01
Treating “approved” as entitlement. If your register shows “approved” next to an item, that word proves less than you think. Approval could not turn in-scope work into a variation (Kaloriziko (No 2) at [118]).
- 02
Relying on the rescue doctrines by choice. Recovery without a written direction depends on rescue doctrines: expensive, uncertain and fact-hungry. The operational answer is the contract's own tool.
- 03
Folding time-related costs into the variation price. State time-related components separately in each variation build-up to avoid prolongation double-recovery.
Checklist
- Run the variation register as an entitlement document. Every direction (written and oral-confirmed), its scope basis, pricing status under the cl 36.4 hierarchy, approval status, and now a scope column: why is this item outside the contract scope, and was cl 36 followed? After Kaloriziko, that column is real money.
- Price before performance, and seek finality wording.Pre-agreement under cl 36.4(a) avoids the valuation fight; an express term that agreed variation values are final and binding (not “on account”) and a scope analysis on file avoid the Kaloriziko fight. Negotiate it into the amendments, or at least into individual variation agreements for significant items.
- Confirm every oral direction in writing within 24 hours. Liebe v Molloy and Update Constructions exist for the breakdown cases. The 24-hour written-confirmation habit, the cl 20 confirmation demand, and the notice register make them unnecessary, and they are the difference between contractual entitlement and a claim for work outside the contract, or an estoppel argument.
- Substantiate like it's a claim, because it is. Each variation file: the direction, the scope analysis (why this is extra), the build-up (quantities, rates, time-related components stated separately to avoid prolongation double-recovery), and contemporaneous cost capture for daywork-style items.
- Watch the omissions. A principal omitting work to give it elsewhere is in Reed & Stuart territory; a contractor watching scope migrate to others should say so in writing immediately: the breach is in the redirection, and silence reads as acquiescence.
When to get advice
Get advice when work has been done on an oral direction that was never confirmed, when an approved or paid item may sit within the contract scope, when work you priced is omitted or moved to another contractor, and before the final account on any contract whose progress payments are on account. The answer turns on the wording of your contract and how it has been administered.
Sources
- 1Kaloriziko Pty Ltd as trustee for Ryde Combined Unit Trust v Calibre Construction Group Pty Ltd (No 2) [2025] NSWCA 259Mitchelmore JA, Kirk JA and Adamson JA, 5 December 2025.
- 2Calibre Construction Group Pty Ltd v Kaloriziko Pty Ltd as trustee for Ryde Combined Unit Trust [2025] NSWSC 593Stevenson J, 11 June 2025.
- 3Liebe v Molloy (1906) 4 CLR 347; [1906] HCA 67Official copy not located; checked against a copy sourced from AustLII.
- 4Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251Report citation, and the account of the decision given here, taken from the Court of Appeal's description in Trimis v Mina [1999] NSWCA 140 at [57] to [61]; the 1990 judgment itself has not been read.
- 5Wegan Constructions Pty Ltd v Wodonga Sewerage Authority [1978] VR 67Checked against [1978] VR 67 (AustLII, VicRp extract) on 15 October 2026.
- 6Commissioner for Main Roads v Reed & Stuart Pty Ltd (1974) 131 CLR 378; [1974] HCA 53Checked against the judgment on AustLII on 15 October 2026.
- 7Standards Australia, AS 4000-1997 General Conditions of Contract cls 20, 36.1, 36.4, 37.2Paraphrased, not quoted.
Malachy Mullin BSc (Hons) MRICS ACIArb
Chartered Quantity Surveyor and Director of SUMIT, a firm regulated by RICS.
Related service: Claims and variations
This article is general information about the law as at the last reviewed date. It is not legal advice, and it is not advice on your contract. For advice on a specific contract or dispute, speak to your lawyers. SUMIT provides commercial and claims advice; it does not provide legal advice.