Skip to content
SUMIT
Menu

InsightsCase notePublished Last reviewed 6 minute read

Time bars defeated delay claims even where the head contractor caused the delay

In CMA Assets v John Holland [No 6] [2015] WASC 217, the Supreme Court of Western Australia accepted that John Holland had delayed its demolition subcontractor, but the delay claims failed because the notices did not comply with the subcontract. A clause expressly excluding the prevention principle was held effective.

By Malachy Mullin, Director

In brief

  1. 01Strict compliance with notice provisions, timing and content, was a condition precedent; claims failed despite the court accepting the head contractor caused delay (CMA Assets [2015] WASC 217).
  2. 02A clause expressly excluding the prevention principle is effective: liquidated damages ran even for delay caused by the other party (at [865]). On the facts, the liquidated damages cap would have been reached even if every extension CMA claimed had been granted, because completion was not achieved in 2007 (at [433], [880]).
  3. 03The unilateral power to extend (clause 10.14) imposed no obligation on John Holland to exercise it, and the court found no basis in the contract to limit it (at [431] to [432]): do not rely on such powers.
  4. 04The defence is administrative: notice matrix, templates, multi-clock diary triggers and a live register.

Who needs to know: Commercial managers, contract administrators, project directors and in-house counsel who give, receive or assess extension of time notices, for head contractors and subcontractors.

Background

In CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] [2015] WASC 217, the Supreme Court of Western Australia accepted that the subcontractor really was delayed, and that the head contractor caused much of it. The delay claims still failed, comprehensively, because the notices did not comply with the subcontract.

John Holland held the contract to upgrade and extend a wharf at Finucane Island, Port Hedland, for BHP Billiton Iron Ore interests, reconstructing a berth for larger vessels. In 2006 it subcontracted CMA Assets to demolish the existing berth structures, including berthing and mooring dolphins, for $10.4 million. Completion was due on 14 March 2007; the court found it was not achieved in 2007 (at [880]).

CMA's difficulties were real: the reinforcement in several dolphins differed materially from the drawings, defeating its blasting methodology (and leaving large debris blocks on the seabed, in breach of the subcontract); John Holland failed to relocate a shiploader, blocking a phase of the works for some three months; and access to other work fronts was denied or deferred for further extended periods. CMA claimed roughly $8.1 million in variations and delay costs; its formal EOT claim for the shiploader delay sought 101 days and $4,428,459 in delay costs. John Holland counterclaimed, including the cost of removing the seabed debris and liquidated damages.

  • Shiploader move

    Scheduled 29 Jan 2007, moved 9 May 2007

    Shiploader move: scheduled for 29 January 2007, moved on 9 May 2007, 101 days late.
  • First notice of intention

    Given 21 Feb 2007

    CMA's first notice of intention to claim an extension for the shiploader delay, given on 21 February 2007, which the court found well outside the time prescribed.
  • Formal EOT claim

    Dated 3 Aug 2007

    CMA's formal extension of time claim for the shiploader delay, 3 August 2007: 101 days and $4,428,459 in delay costs.

Fig. 1The shiploader was moved 101 days after its scheduled date. CMA's first notice of intention to claim came on 21 February 2007, which the court found well outside the prescribed time; the formal claim followed on 3 August 2007.

Calendar days from the scheduled shiploader move on 29 January 2007, drawn to scale. The Date for Completion was 14 March 2007.

Source: CMA Assets [2015] WASC 217 at [90], [341], [343], [366], [376].

The subcontract's notice regime was layered and specific. Clause 10.12 required notice as soon as CMA became aware of the likelihood of delay; notice of intention to claim an EOT within 7 days of the occurrence of the cause, with an estimate of the delay and the steps to minimise it; and a detailed written claim within 14 days of commencement of the delay, setting out the facts, the days claimed and the effect on the approved programme. Clause 10.13 said it plainly: a subcontractor that failed to comply with clause 10.12 “shall have no entitlement to an extension of time”.

  1. 01

    Aware of likely delay

    Notify John Holland as soon as CMA becomes aware of the likelihood of delay (cl 10.12(b)(i)).

  2. 02

    Cause occurs

    Notice of intention to claim within 7 days, with the cause, an estimate of the delay and the steps to minimise it (cl 10.12(b)(iv)).

  3. 03

    Delay commences

    A written claim within 14 days, with the facts, the days claimed and a marked-up programme (cl 10.12(b)(v)).

  4. 04

    While the delay continues

    Updates every 5 days until the effects cease (cl 10.11).

  5. 05

    Non-compliance

    No entitlement to an extension of time, and the prevention principle excluded (cl 10.13; at [865]).

  6. 06

    John Holland's power

    John Holland may extend time anyway (cl 10.14) but is not obliged to (at [431]).

Fig. 2The subcontract ran separate notice clocks from separate triggers, and clause 10.13 removed any entitlement for non-compliance.

A summary of the clauses as quoted in the judgment, not their full text.

Source: CMA Assets [2015] WASC 217 at [266], [370], [431], [865]; subcontract cll 10.11 to 10.14.

The issue

Was strict compliance with the notice regime a condition precedent to EOT and delay-cost entitlement? Did it matter that John Holland itself caused key delays: could the prevention principle defeat the time bar and the liquidated damages? And could waiver, estoppel or an implied duty to exercise the unilateral extension power in good faith rescue the claims?

The decision

Allanson J enforced the regime as written. Compliance with clause 10.12, as to both timing and content, was a condition precedent. CMA's first shiploader notice came well outside the prescribed time. The other claims failed on timing, content or both, and for two delays no compliant EOT notice was given at all (at [378], [392] to [394], [415] to [416]). The judge accepted the strict operation of the clauses was harsh, but not so purposeless or absurd as to compel a different construction. The claims failed even though the court found, on the evidence, that John Holland's conduct had in fact delayed CMA.

The prevention principle argument fared worse. Following the orthodox line (a contractor with an available EOT mechanism it failed to use cannot call the completion obligation into question), the court went on to hold (at [865]) that clause 10.13 expresslyexcluded the prevention principle and was effective in doing so. CMA was precluded from extensions and liable for liquidated damages “even where the relevant delay has been caused by John Holland”. The estoppel case failed on the facts; the unilateral power to extend (clause 10.14) imposed no obligation on John Holland to exercise it, and the court found no basis in the contract to limit it (at [431] to [432]).

A clause stating that a subcontractor who fails to comply with the notice regime has no entitlement to an extension of time expressly excluded the prevention principle, and was effective in doing so.
CMA Assets [2015] WASC 217 at [865]. A summary, not a quotation.

John Holland had conceded, subject to set-off, about $8.1 million for the balance of the subcontract sum and the bank guarantees (at [18]). Beyond that, CMA recovered only Variation 79, $639,568.21 (at [906]). John Holland's counterclaim succeeded for $5,386,612 in damages (plus crew costs still to be converted to Australian dollars) and $1,182,700 in liquidated damages, the capped maximum, and it could set those sums off (at [905], [907]).

Why it matters

If you want one Australian case to make a project team take notices seriously, use this one. The decision goes a step further than most time-bar authorities: it held that a clause expressly excluding the prevention principle is effective, so the subcontractor was liable for liquidated damages even for delay the head contractor caused.

Practical steps for contractors and subcontractors

  1. 01

    “They know we’re delayed” is not a notice. The principal's actual knowledge of the delay does nothing. Entitlement lives in the notice document: served in time, to the right person, with every prescribed content element. Rimfire Energy v BSF Co (No 2) [2025] FCA 384 has since made the same point at Federal Court level: content gaps are as fatal as late service.

  2. 02

    Multi-stage notice regimes need a process, not a memory. Clause 10.12 had three clocks running off different triggers (awareness, occurrence, commencement) plus content requirements. That is unmanageable by recollection. It is trivially manageable with a notice matrix, standing templates and a register reviewed weekly.

  3. 03

    Assume the prevention principle will not save you. CMA Assets held that parties can contract out of it with clear words (at [865]), and modern amended contracts routinely do. The only reliable response to principal-caused delay is the same as for any other delay: notice, on time, in full.

  4. 04

    Time bars cut twice. CMA didn't just lose its claims: it paid liquidated damages for delay that included delay John Holland caused (at [865]), plus the counterclaim. On the facts, the liquidated damages cap would have been reached even if every extension CMA claimed had been granted, because completion was not achieved in 2007 (at [433], [880]). When pricing a subcontract with an aggressive notice regime, price the administration to comply with it; the alternative is pricing the double jeopardy.

  5. 05

    Respondents and head contractors: the regime is your audit checklist. Every incoming claim should be tested against each notice element before any merits engagement. This decision is the template for that exercise.

  • Rimfire Energy Pty Ltd v BSF Co Pty Ltd (No 2) [2025] FCA 384 (notice content; power purchase agreements, not a construction subcontract).

Sources

  1. 1CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] [2015] WASC 217AustLII judgment text and AustLII WA Court of Appeal listings checked 15 October 2026; the WA eCourts Portal record was not opened (it requires terms to be accepted).
  2. 2Rimfire Energy Pty Ltd v BSF Co Pty Ltd (No 2) [2025] FCA 384O'Callaghan J, 22 April 2025.

Malachy Mullin BSc (Hons) MRICS ACIArb

Chartered Quantity Surveyor and Director of SUMIT, a firm regulated by RICS.

0452 549 257malachy@sumitconsulting.com.auExpert CV

Related service: Claims and variations

This article is general information about the law as at the last reviewed date. It is not legal advice, and it is not advice on your contract. For advice on a specific contract or dispute, speak to your lawyers. SUMIT provides commercial and claims advice; it does not provide legal advice.

Insights by emailFree

Practical notes on contracts, claims and payment law

New case notes and guidance on security of payment, claims, variations and contract administration in Australian construction, in one email, no more than once a month. Written for contractors, subcontractors, principals and their lawyers.

Written by Malachy Mullin MRICS ACIArb, Director of SUMIT.

Tell us more (optional)

No more than one Insights email a month. Every email has an unsubscribe link. Your details are handled as our privacy policy explains.