InsightsCase notePublished Last reviewed 6 minute read
After repudiation, the contract price disciplines what terminated work is worth
In Mann v Paterson Constructions [2019] HCA 32, the High Court closed the old escape from a bad bargain: terminate and claim a generous quantum meruit. The contract price now disciplines what terminated work is worth.
By Malachy Mullin, Director
In brief
- 01No quantum meruit for work where the contractual right to payment has accrued; accrued stages are contract-remedy territory (Mann v Paterson [2019] HCA 32, unanimous).
- 02For incomplete stages, restitution survives but is capped by the contract price: absolutely for Gageler J (at [102], [105]); prima facie, with exceptions left open, for Nettle, Gordon and Edelman JJ (at [215]–[216]).
- 03The Renard/Sopov“generous quantum meruit” era is over; the bargain disciplines valuation.
- 04Where s 38 applies, a builder who skips the statutory process can recover for those variations only through VCAT's exceptional circumstances or hardship gateway (s 38(6)(b), (7); [59], [160]).
Who needs to know: Commercial managers, quantity surveyors, contract administrators and in-house counsel who value terminated work or administer variations, for builders, subcontractors and principals.
Background
In March 2014, Peter and Angela Mann engaged Paterson Constructions under a major domestic building contract governed by the Domestic Building Contracts Act 1995 (Vic) to build two double-storey townhouses at Blackburn, Melbourne, for a fixed price of $971,000, payable by staged progress payments. During the works the Manns orally requested 42 variations, which the builder carried out, without the written notices the contract and s 38 of the Act required.
After the first unit was handed over, the builder claimed roughly $48,000 for that unit's variations. Relations collapsed; in April 2015 the Manns purported to terminate for the builder's repudiation and excluded it from site. The builder treated that purported termination as itself repudiatory and accepted it. VCAT found the Manns had wrongfully repudiated, and the builder elected quantum meruit. VCAT valued the work, before defects, at $1,722,611 against the $971,000 price, and awarded $660,526.41, substantially more than contract damages would have produced. The Victorian Supreme Court and Court of Appeal, bound by the old line of authority, upheld the approach. The High Court allowed the appeal and remitted the matter: Mann v Paterson Constructions Pty Ltd [2019] HCA 32.
| Item | Amount | Source |
|---|---|---|
| Contract price (including GST) | $971,000.00 | At [111] |
| Builder's quantity surveyor, interim report | $1,898,673.00 | At [136] |
| VCAT: value of the work assessed without defects | $1,722,611.00 | At [139] |
| Less defects | ($116,297.59) | At [139] |
| Benefit to the owners | $1,606,313.41 | At [139] |
| Less net amount paid | ($945,787.00) | At [139] |
| Amount due to the builder (VCAT) | $660,526.41 | At [139] |
Source: Mann [2019] HCA 32 at [111], [136], [139]; orders 1 and 2(c).
The issue
Three questions of real commercial consequence: may a builder who accepts a repudiation claim restitution as an alternative to contract damages at all; if so, for which work; and is the recovery capped by the contract price? A fourth, specific to domestic building work: can a builder recover anything for variations that bypassed the statutory written-notice regime?
The decision
The Court was unanimous on the central restriction: where the contractual right to payment for a stage had already accrued (completed stages), there is no restitutionary alternative. Termination for repudiation operates prospectively; accrued rights survive and are enforced as debt or damages under the contract. The old reasoning that termination “rescinded” the contract and left the work unpaid-for on a clean slate (the rescission fallacy) was rejected.
Where a builder's contractual right to payment for a stage has accrued before it terminates for repudiation, there is no restitutionary claim for that work. The builder is confined to its contract remedies in debt or damages.
For the incomplete stage, the Court divided. Kiefel CJ, Bell and Keane JJ would have abolished the quantum meruit alternative outright. The majority preserved it in confined form: Gageler J held recovery cannot exceed the portion of the contract price attributable to the work; Nettle, Gordon and Edelman JJ held the amount should prima facie not exceed a fair value calculated in accordance with the contract price or the appropriate part of it. The practical effect either way: the bargain disciplines the valuation. Earlier authority permitting recovery above the contract rate (the Renard and Sopov v Kane line) no longer represents the law.
On the variations, the Court unanimously held s 38 of the Victorian Act covers the field: a builder who performs domestic building variations without the statutory process is confined to the Act's narrow gateway, and common-law restitution is excluded. Forty-two oral variations, recoverable (if at all) only through a provision the builder had not engaged.
| Work | Kiefel CJ, Bell and Keane JJ | Gageler J | Nettle, Gordon and Edelman JJ |
|---|---|---|---|
| Completed stages (right to payment accrued) | Contract remedies only (at [27]) | Contract remedies only (at [62]) | Contract remedies only (at [179]) |
| Incomplete stage | No restitution; contract damages (at [4], [53]) | Restitution, not exceeding the portion of the contract price attributable to the work (at [102], [105]) | Restitution, prima facie not exceeding a fair value calculated in accordance with the contract price (at [215] to [217]) |
| Variations done without the s 38 process | Section 38 route only (at [4]) | Section 38 route only (at [59]) | Section 38 route only (at [160]) |
Source: Mann [2019] HCA 32 at [4], [27], [53], [59], [62], [102], [105], [160], [179], [215] to [217].
Why it matters
For decades, Australian builders held a famous escape hatch: if the principal repudiated, the builder could terminate, ignore the contract price, and claim a “quantum meruit” (the reasonable value of the work) which courts sometimes assessed at figures far above the bargain. Underpriced job, difficult client, repudiation: the termination could be worth more than performance. Mann closed that hatch. The High Court confined restitution after repudiation to a narrow field and anchored its value to the contract, ending one of construction law's most commercially distorting doctrines.
Victoria is replacing ss 37 and 38. For contracts entered into from commencement (1 December 2026 at the latest), a variation needs a signed written agreement, and a builder who skips it can recover only if VCAT finds exceptional circumstances or hardship (Domestic Building Contracts Amendment Act 2025 (Vic) ss 2(3), 17; new s 37(3) to (5), s 139).
Practical steps for contractors and subcontractors
- 01
Terminated work is now valued through the contract, not around it. For completed stages or milestones, entitlement is the accrued contract amount. For work in progress, expect any restitutionary assessment to be built from the contract price and rates: schedule of rates, milestone breakdowns, the priced bill. The “independent reasonable value” report untethered from the bargain is a relic.
- 02
Stage and milestone payment structures shrink the battlefield. The more granular the payment structure, the more of the work sits behind accrued rights where only contract remedies run. That is now a drafting consideration: principals benefit from fine-grained stages; contractors should at least understand what the structure does to their termination position.
- 03
Repudiation maths has changed for principals too. Before Mann, repudiating against an underpriced contractor risked a quantum meruit windfall to the other side. That in terrorem effect is gone, but contract damages, including loss of profit on the balance of the works, remain fully alive.
- 04
Document variations or lose them. The s 38 holding is Victorian, but domestic building regimes in other states impose their own formalities, and commercial contracts have their own written-direction machinery. Mann's variation holding turns on the Victorian Act, but the lesson travels: the contract's written-direction machinery is the safe route everywhere. Forty-two oral variations should never exist on any well-administered project: the variation register, signed directions and contemporaneous pricing are the entitlement.
- 05
Quantum discipline applies to claim preparation now. When valuing termination accounts or supporting experts in repudiation disputes, start from the contract's own pricing architecture and build any departures as exceptions requiring justification, because that is precisely how a tribunal will now test the figure.
Related legislation and cases
- Domestic Building Contracts Act 1995 (Vic) s 38 (variations), including s 38(6)(b) and (7) (recovery through VCAT).
- Domestic Building Contracts Amendment Act 2025 (Vic) ss 2(3), 17, 20 (new ss 37, 38 and 139).
- Mann v Paterson Constructions Pty Ltd [2018] VSCA 231 (the decision appealed from).
- Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234.
- Sopov v Kane Constructions Pty Ltd [No 2] (2009) 24 VR 510.
Sources
- 1Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560; [2019] HCA 32Official reasons with paragraph numbers. Hearing date (14 May 2019) checked on the High Court case page (M197/2018), 15 October 2026. Print report not seen; citation confirmed from North Queensland Pipeline No 1 v QNI Resources [2021] QSC 190 (AustLII).
- 2Mann v Paterson Constructions Pty Ltd [2018] VSCA 231Checked on AustLII, 15 October 2026 (Kyrou, McLeish and Hargrave JJA, 12 September 2018).
- 3Paterson Constructions Pty Ltd v Mann (Building and Property) [2016] VCAT 2100Checked on AustLII, 15 October 2026 (facts of termination and exclusion from site at [2]).
- 4Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234Print report not seen; citation confirmed from [2019] HCA 32 fn 157, 182 (AustLII, 15 October 2026). Not checked against the judgment.
- 5Sopov v Kane Constructions Pty Ltd [No 2] (2009) 24 VR 510Print report not seen; citation confirmed from [2019] HCA 32 fn 10, 159, 168 (AustLII, 15 October 2026). Not checked against the judgment.
- 6Domestic Building Contracts Act 1995 (Vic) s 38Authorised version 094 (from 1 July 2026) still contains the old s 38.
- 7Domestic Building Contracts Amendment Act 2025 (Vic) ss 2(3), 17, 20Act No 36 of 2025, assented 16 September 2025.
Malachy Mullin BSc (Hons) MRICS ACIArb
Chartered Quantity Surveyor and Director of SUMIT, a firm regulated by RICS.
Related service: Dispute avoidance and resolution support
This article is general information about the law as at the last reviewed date. It is not legal advice, and it is not advice on your contract. For advice on a specific contract or dispute, speak to your lawyers. SUMIT provides commercial and claims advice; it does not provide legal advice.