Skip to content
SUMIT
Menu

InsightsCase notePublished Last reviewed 6 minute read

A Queensland court stayed an adjudication award the builder was unlikely to repay

In Taringa Property Group v Kenik [2024] QSC 327, Hindman J stayed enforcement of a $4,218,787.02 adjudication award against a builder that was not in liquidation. The builder was wound up on 20 February 2025.

By Malachy Mullin, Director

In brief

  1. 01A Queensland court may stay enforcement of an adjudication award where there is a very high risk the claimant cannot repay after final determination; liquidation is not a prerequisite (Taringa v Kenik [2024] QSC 327 at [23], [43]).
  2. 02The respondent's playbook: the adjudicated amount already in court (compulsory when the judgment is challenged), the substantive case started, and the distress proved with documents.
  3. 03Conditions follow: costs released, subcontractor amounts preserved, interest topped up, undertakings given.
  4. 04The claimant's subsequent winding up (and the refusal of leave to continue against it, [2025] QSC 222) shows both the stay's value and its limits.

Who needs to know: Commercial managers, contract administrators, in-house counsel and finance teams at principals and head contractors that pay adjudicated amounts in Queensland, and at claimants whose finances are under strain.

Background

“Pay now, argue later” is the security of payment bargain: the respondent pays the adjudicated amount immediately and recovers any overpayment after final determination. The bargain has a known failure mode: what if, by the time you win the final argument, the claimant has no money to repay? Taringa Property Group Pty Ltd v Kenik Pty Ltd[2024] QSC 327 gives one Queensland answer to that question: the court stayed enforcement of a $4,218,787.02 adjudication award because of the claimant's perilous financial position, even though the claimant was not yet in liquidation. The sequel proved the point: the claimant was wound up two months later.

Taringa Property Group engaged Kenik under a design-and-construct contract (August 2020, roughly $13.6 million) for a retail development at Taringa in Brisbane. After Taringa terminated the contract on 29 August 2023, Kenik served a payment claim of about $9.7 million; Taringa's payment schedule responded nil. In February 2024 an adjudicator awarded Kenik $4,218,787.02, and the adjudication certificate was filed as a judgment. Taringa paid the amount (with interest and costs) into court and applied on two fronts: to set the determination aside for jurisdictional error, which failed, and for a stay of enforcement pending its substantive proceeding claiming overpayment and damages.

The stay evidence was the heart of it. Kenik had about $9,000 cash at bank. Its claimed net current assets rested on around $2 million of disputed receivables. It carried nearly $7 million in liabilities, many of them long-overdue trade debts on projects completed years ago, its QBCC licence had been suspended for failing minimum financial requirements and later surrendered, it had stopped trading, its director was personally funding it, and a creditor's winding-up application was already on foot. Hindman J's assessment was blunt: it was difficult to see a path that did not end in external administration.

The issue

Queensland authority (the R J Neller Building Pty Ltd v Ainsworth [2008] QCA 397 line) treats the risk of claimant insolvency during the interim period as a risk the legislation deliberately allocates to the respondent. Recognised grounds for a stay were narrow: claimants who restructured their finances to defeat recovery, claimants engaged in delaying tactics, or claimants already in liquidation. Kenik was in none of them. The question: can deep financial distress short of liquidation justify a stay?

The decision

Hindman J granted the stay on conditions, in reasons given ex tempore on 23 December 2024, although the claimant was not in liquidation; counsel for Kenik submitted it would be the first such case in Queensland (at [49]). Most of the discrete factors actually leaned against Taringa: the adjudicator had substantially accepted Kenik's claim on the merits, the strength of Taringa's substantive case was unclear, the policy of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (the BIF Act) carries significant weight, and Taringa's own withholding of payment had contributed to Kenik's decline (at [25] to [28]). What carried the day was the core risk: a very high likelihood that, without a stay, the “interim” payment would in substance become final and unrecoverable (at [43], [48]).

A claimant need not be in liquidation before enforcement of an adjudication judgment can be stayed. The stay was granted because there was a very high likelihood that, without it, the interim payment would in substance become final and unrecoverable.
Taringa v Kenik [2024] QSC 327 at [23], [43], [48]. A summary, not a quotation.

The conditions show the balance being struck rather than abandoned. The adjudication costs component was released to Kenik immediately; a tranche referable to subcontractor charges was preserved; the substantive balance stayed in court pending trial; Taringa was required to top up interest; the usual undertaking as to damages applied; and Kenik had liberty to apply, including in relation to litigation funding. Kenik's appeal (CA 224/25) was brought to an end by consent in August 2025 ([2025] QSC 222 at [23], [27]).

Table 1The court kept the balance of the adjudicated amount in court, but released the adjudication costs to Kenik and kept a separate tranche for subcontractors' charges.
ItemWhat the court orderedReference
Balance of the adjudicated amountStayed and held in court until Taringa's proceeding BS 3773/24 is determined or further order.Orders 1 and 2
Adjudication costs, $91,076.36Released to Kenik (the adjudicator's fees and lodgement fee). The court raised this carve-out itself.Order 3; [11]
Subcontractors' charges, $803,267.16Kept in court for subcontractors' charges.Order 4; [9]; BIF Act ss 97B, 126
InterestTaringa to top up interest to 30 June 2026. It paid $1,597,940.94 on 31 January 2025.[10]; [2025] QSC 222 at [18]
Undertaking as to damagesThe usual undertaking applied.[10], [44] to [47]
Liberty to applyReserved, including in relation to litigation funding.Order 7; [12], [13]

Source: Taringa v Kenik [2024] QSC 327, orders 1 to 4 and 7, at [9] to [13], [44] to [47]; Taringa v Kenik [2025] QSC 222 at [18]; Building Industry Fairness (Security of Payment) Act 2017 (Qld) ss 97B, 126.

Why it matters

In February 2025, Kenik was wound up in insolvency on the pre-existing creditor's application: over 200 unsecured creditors, more than $10 million owed. And in Taringa Property Group Pty Ltd v Kenik Pty Ltd [2025] QSC 222, Taringa was refused leave to continue its substantive proceeding against the company in liquidation, being left to the proof-of-debt process. The stay had protected the fund; it could not manufacture a solvent counterparty to litigate against.

  • Payment claim to adjudication

    Claim served 8 Sep 2023; decision 14 Feb 2024

    Payment claim of $9,689,767.44 served on 8 September 2023; adjudication decision of $4,218,787.02 on 14 February 2024.
  • Taringa's set-aside challenge

    Filed 23 Feb 2024; $4,825,708.11 paid into court 4 Mar 2024

    Taringa applied on 23 February 2024 to set the adjudication judgment aside and paid $4,825,708.11 into court on 4 March 2024. The challenge failed on 6 December 2024 in [2024] QSC 298.
  • Taringa's claim against Kenik

    BS 3773/24, overpayment and damages, filed 26 Mar 2024

    Taringa started its substantive proceeding, BS 3773/24, on 26 March 2024. On 19 September 2025 it was refused leave to continue it against Kenik in liquidation.
  • Stay of enforcement

    Heard 19 Dec 2024; granted ex tempore 23 Dec 2024

    The stay application was heard on 19 December 2024 and granted on 23 December 2024.
  • Kenik's appeal

    CA 224/25, filed 20 Jan 2025; ended by consent

    Kenik filed its appeal on 20 January 2025. It was brought to an end by consent in August 2025; [2025] QSC 222 at [27] records it dismissed by consent on 14 August 2025.
  • Kenik in liquidation

    Wound up 20 Feb 2025

    Kenik was wound up on 20 February 2025 and remained in liquidation to September 2025.

Fig. 1Enforcement was stayed on 23 December 2024. Kenik was wound up on 20 February 2025, about eight weeks later, and in September 2025 Taringa was refused leave to continue its claim against the company in liquidation.

Bars are drawn to scale by calendar date. The stay hearing (19 December 2024) and the stay orders (23 December 2024) are shown as one short bar.

Source: Taringa v Kenik [2024] QSC 327 at [3] to [8]; Taringa v Kenik [2025] QSC 222 at [12], [23], [24], [27], [100] to [101].

Practical steps for contractors and subcontractors

  1. 01

    Respondents facing a distressed claimant now have a real, evidenced pathway. The elements that worked here: the adjudicated amount was already in court (BIF Act s 93(4)(b) requires this when a respondent challenges the judgment); commence the substantive proceeding immediately (the stay protects pending something); and assemble concrete solvency evidence: licence suspensions, winding-up applications, financial statements, non-trading status. Speculation about financial weakness gets nowhere; a documented file met the heavy onus.

  2. 02

    Expect conditions, not a free pass. Interest top-ups, carve-outs for costs and subcontractor-bound amounts, undertakings as to damages. The court is preserving a fund, not punishing the claimant.

  3. 03

    Claimants in distress: the decision cuts both ways. Financial difficulty now invites stay applications even without liquidation, but Hindman J cautioned that such stays will be “a small number of cases” and that fishing applications can attract indemnity costs (at [50]). Counter-strategies visible in the case: evidence of solvency and trading capacity, the argument that the respondent's own non-payment caused the distress (it weighed in Kenik's favour on the discretionary factors), and carve-outs: the court released the adjudication costs to Kenik of its own motion and left access for litigation funding open on liberty to apply.

  4. 04

    The risk allocation conversation belongs earlier. For principals, counterparty financial standing at award and during delivery is the cheapest protection: by the time you are resisting enforcement, the money you are protecting is already at risk. Payment-behaviour monitoring, security adequacy and trust/charge regimes all sit upstream of this fight.

  5. 05

    A stay protects the fund, not the outcome. The [2025] QSC 222 sequel is the sobering coda: once the claimant entered liquidation, the respondent's “argue later” became a proof of debt. Win the stay, but plan the endgame, including what a liquidator does to your cross-claims.

  • Building Industry Fairness (Security of Payment) Act 2017(Qld) ss 93 (adjudication certificate filed as a judgment; payment into court on an application to set it aside), 97B and 126 (subcontractors' charges).
  • Uniform Civil Procedure Rules 1999 (Qld) r 800 (stay of enforcement).
  • Corporations Act 2001 (Cth) ss 459A (winding up in insolvency), 471B (leave to proceed against a company in liquidation).
  • R J Neller Building Pty Ltd v Ainsworth [2008] QCA 397; [2009] 1 Qd R 390.
  • Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 298 (the failed jurisdictional error challenge).
  • Taringa Property Group Pty Ltd v Kenik Pty Ltd [2025] QSC 222 (leave to proceed refused).

Sources

  1. 1Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 327Hindman J, 23 December 2024 (ex tempore).
  2. 2Taringa Property Group Pty Ltd v Kenik Pty Ltd [2025] QSC 222Williams J, 19 September 2025.
  3. 3Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 298Checked on AustLII, 15 October 2026 (Hindman J, 6 December 2024). Queensland Judgments copy not checked.
  4. 4R J Neller Building Pty Ltd v Ainsworth [2008] QCA 397; [2009] 1 Qd R 390Keane and Fraser JJA and Fryberg J, 9 December 2008. Decided under the predecessor Building and Construction Industry Payments Act 2004 (Qld).
  5. 5Building Industry Fairness (Security of Payment) Act 2017 (Qld) ss 93, 97B, 126Section 93 checked in the reprint current from 28 April 2026. Sections 97B and 126 as cited in the judgments.
  6. 6Uniform Civil Procedure Rules 1999 (Qld) r 800As cited in [2024] QSC 327 at [15] and order 2. Rule heading checked on Queensland Legislation, 15 October 2026.
  7. 7Corporations Act 2001 (Cth) ss 459A, 471BAs cited in [2025] QSC 222 at [24], [30]. Section headings checked on AustLII, 15 October 2026; Federal Register of Legislation not checked.

Malachy Mullin BSc (Hons) MRICS ACIArb

Chartered Quantity Surveyor and Director of SUMIT, a firm regulated by RICS.

0452 549 257malachy@sumitconsulting.com.auExpert CV

Related service: Security of payment

This article is general information about the law as at the last reviewed date. It is not legal advice, and it is not advice on your contract. For advice on a specific contract or dispute, speak to your lawyers. SUMIT provides commercial and claims advice; it does not provide legal advice.

Insights by emailFree

Practical notes on contracts, claims and payment law

New case notes and guidance on security of payment, claims, variations and contract administration in Australian construction, in one email, no more than once a month. Written for contractors, subcontractors, principals and their lawyers.

Written by Malachy Mullin MRICS ACIArb, Director of SUMIT.

Tell us more (optional)

No more than one Insights email a month. Every email has an unsubscribe link. Your details are handled as our privacy policy explains.