Skip to content
SUMIT
Menu

InsightsGuidancePublished Last reviewed 6 minute read

A valid NSW payment claim needs the right timing, content and service

For contracts entered into on or after 21 October 2019, a payment claim must be served on time, identify the work, state the claimed amount and say it is made under the Act. Here is the checklist to run before serving.

By Malachy Mullin, Director

Key takeaways

  1. 01Validity elements: timing under s 13(1A) to (1C), identification of work, claimed amount, the “made under the Act” statement, one claim per month, 12-month long-stop.
  2. 02Head contractors must attach a supporting statement; omission is an offence but does not invalidate the claim (TFM Epping [2020] NSWCA 93).
  3. 03A missed payment schedule makes the respondent liable for the full claimed amount with cross-claims and contract defences barred in the debt recovery proceedings (ss 14(4), 15(2)(a)(i), 15(4)(b)).
  4. 04Time runs from actual service; a contractual clause deeming later receipt cannot extend the respondent's 10-business-day window under s 14(4)(b)(ii) (Roberts Co v Sharvain [2025] NSWCA 161).

Who needs to know: Commercial managers, contract administrators and quantity surveyors who prepare or serve payment claims in NSW, for head contractors and subcontractors, and the people who receive them.

Context

The Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) gives contractors and subcontractors some of the fastest debt-recovery machinery available to them, but the machine only starts if the payment claim is valid. Validity disputes are where respondents win without ever arguing the merits, and where claimants lose months of cashflow to defects that take minutes to avoid.

This is the practitioner's checklist, current for contracts entered into on or after 21 October 2019 (the post-amendment regime; older contracts still run on reference dates: see our note on Southern Han).

The claimant must have undertaken work under a construction contract, and serves the party liable to pay

The entitlement belongs to a person who has undertaken to carry out construction work (or supply related goods and services) under a construction contract, written or oral, and who is or claims to be entitled to a progress payment (ss 7(1), 8(1), 13(1)). The claim is served on the person liable to pay.

Validity fights at this threshold often involve whether there is a “construction contract” at all, or whether the arrangement falls within an exclusion such as s 7(2)(c). Informal development arrangements are dangerous territory on both counts (see Kwik Flo Pty Ltd v SE Ware Street Dev Pty Ltd [2026] NSWCA 9).

A claim can be served from the last day of each named month, once a month, within the long-stop

For post-October 2019 contracts, a payment claim may be served on and from the last day of the named month in which the work was first carried out, and on and from the last day of each subsequent month (s 13(1A)), or from an earlier date if the contract provides one (s 13(1B)). On termination, a claim may be served on and from the date of termination (s 13(1C)).

Three limits sit around that entitlement:

  • One claim per named month for work in that month (s 13(5), a default the contract can vary), though a claim can include amounts from previous months and re-claim previously claimed amounts (s 13(6)). Serving two claims for the same month invites a validity attack on the second.
  • The long-stop: a claim must be served within the period allowed by the contract or 12 months after the work was last carried out, whichever is later (s 13(4)).
  • Service means actual service.The clock consequences run from when the claim actually arrives (uploaded to the contractual platform, capable of retrieval), and a contractual clause deeming later receipt cannot extend the respondent's 10-business-day window under s 14(4)(b)(ii) (Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161 at [36] to [37], [52] to [53]).

The claim must identify the work, state the amount and say it is made under the Act

A valid claim must (s 13(2)):

  1. Identify the construction work (or goods and services) to which it relates. The standard is reasonable identification: enough for the respondent to understand what is being claimed and assess it (Clarence Street Pty Ltd v Isis Projects Pty Ltd(2005) 64 NSWLR 448; [2005] NSWCA 391 at [28] to [31]). Sloppy identification is a frequently argued defect; a claim summary tied to the contract's payment schedule structure, with supporting detail attached, answers it.
  2. Indicate the claimed amount.
  3. State that it is made under the Act.The endorsement was reinstated for post-October 2019 contracts (s 13(2)(c)). The safe form of words: “This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).” Put it on the face of the claim, not buried in a covering email.
Table 1The checks a NSW payment claim must pass under a contract entered into on or after 21 October 2019, and the section that sets each one. The supporting statement is the exception: missing it is an offence, not a defect in the claim.
CheckWhat the Act requiresSection
Month entitlementOn and from the last day of the named month in which the work was first carried out, and of each later month; or an earlier date the contract provides. On termination, from the date of termination.s 13(1A), (1B), (1C)
One claim per monthOne claim for each named month for work in that month, unless the contract provides otherwise. A claim may include amounts from earlier months and re-claim amounts claimed before.s 13(5), (6)
Long-stopWithin the period the contract allows or 12 months after the work was last carried out, whichever is later.s 13(4)
Work identifiedIdentify the construction work (or goods and services) claimed for.s 13(2)(a)
AmountIndicate the claimed amount.s 13(2)(b)
Made under the ActState that the claim is made under the Act.s 13(2)(c)
Supporting statementHead contractor to principal only: a statement in the approved form declaring that subcontractors have been paid amounts due and payable. Omission is an offence, not an invalidity (TFM Epping).s 13(7)
ServiceOn the person who is or may be liable to pay, by a permitted method.ss 13(1), 31(1)

Source: Building and Construction Industry Security of Payment Act 1999 (NSW) ss 13(1) to (7), 31(1), sch 2 cl 6; TFM Epping [2020] NSWCA 93 at [47], [69] to [73].

A head contractor's missing supporting statement is an offence, not an invalidity

A head contractor must not serve a payment claim on the principal unless it is accompanied by a supporting statement in the approved form, declaring that all subcontractors have been paid amounts due and payable (s 13(7)). Two things practitioners get wrong about it:

  • Omission is an offence, not an invalidity. In TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93, the Court of Appeal held a non-compliant supporting statement does not invalidate the payment claim; the sanction is penal (and the penalties are real: up to 1,000 penalty units for a corporation, with a separate offence for knowingly false statements under s 13(8)).
  • It is still not optional. Compliance discipline matters both because of the penalty exposure and because a respondent will happily run the argument and force you to litigate TFM Epping before paying.

A valid claim gives the respondent at most 10 business days to provide a payment schedule

A valid claim puts the respondent to an election with a fuse of at most 10 business days (shorter if the contract requires): provide a payment schedule under s 14, or become liable for the full claimed amount (s 14(4)), recoverable as a debt, with the respondent barred from raising contract defences or cross-claims in the recovery proceedings (s 15(4)(b)). And remember the Act's own calendar: “business day” excludes weekends, public holidays and 27 to 31 December (s 4). (Sch 1 of the Fair Trading and Building Legislation Amendment Act 2026(NSW), not yet commenced, will rename these “working days” without changing the excluded days.)

  1. 01

    Claim can be served

    From the last day of the named month in which the work was first carried out, or an earlier date in the contract (s 13(1A), (1B)); on termination, from the termination date (s 13(1C)).

  2. 02

    Long-stop

    Within the contract period or 12 months after the work was last carried out, whichever is later (s 13(4)).

  3. 03

    Claim served

    By a method in s 31(1); served when it is capable of retrieval (Roberts Co at [36], [50]).

  4. 04

    Schedule due

    By the earlier of the contract time or 10 business days after actual service (s 14(4)(b)); a deeming clause cannot extend it (Roberts Co at [52] to [53]).

  5. 05

    No schedule and no payment

    Recover the claimed amount as a debt, with cross-claims and contract defences barred in those proceedings (s 15(2)(a)(i), (4)(b)), or apply for adjudication (s 15(2)(a)(ii)).

Fig. 1The month of the work fixes when a claim can be served; actual service fixes the respondent's deadline; a missed schedule turns the claim into a debt.

Contracts entered into on or after 21 October 2019. Business days under s 4(1) of the Act exclude weekends, public holidays and 27 to 31 December. Debt recovery also requires that the claimed amount was not paid by the due date (s 15(1)).

Source: Building and Construction Industry Security of Payment Act 1999 (NSW) ss 4(1), 13(1A) to (1C), 13(4), 14(4)(b), 15(1), 15(2)(a), 15(4)(b), 31(1); Roberts Co [2025] NSWCA 161 at [36] to [37], [50], [52] to [53].

Audit every claim before service and keep the evidence of service

  1. 01

    Run a pre-service validity audit, every claim. Sixty seconds against the checklist: month entitlement, one-claim rule, endorsement on the face, work identified against the contract structure, amount stated, supporting statement attached (head contracts), service method per the contract. Make it a standing agenda item in the monthly claim cycle.

  2. 02

    Build the claim for the adjudication you hope to avoid. A claim that identifies work clearly, with substantiation attached, does double duty: it answers the s 13(2)(a) attack and it becomes the spine of any adjudication application that follows.

  3. 03

    Control the service evidence. Serve by every contractually permitted method, capture the transmission record, and diarise the respondent's 10-business-day schedule deadline from the actual service date, including for claims served after hours or on weekends.

Common pitfalls

  1. 01

    Don't manufacture validity problems with multiple claims. Where a claim needs correcting, consider whether the contract permits a further claim in that month (s 13(5)); if not, include the corrected amounts in the next month's claim (s 13(6)) rather than serving a second claim in the same month. Section 13(5) arguments are a gift to respondents.

  2. 02

    Know which regime the contract lives under. Pre-21 October 2019 contracts still require a reference date (Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52). The analysis above does not transplant backwards.

  3. 03

    Endorsement in the covering email only. Put the “made under the Act” statement on the face of the claim, not buried in a covering email.

  4. 04

    Treating the supporting statement as optional. Omission does not invalidate the claim, but it is an offence, and a respondent may still run the argument.

Checklist

Before serving each payment claim:

  • Confirm the contract was entered into on or after 21 October 2019; if not, find the reference date.
  • Confirm the month entitlement: the last day of the named month has arrived, or an earlier contract date applies (s 13(1A), (1B)).
  • Check no other claim has been served for work in the same named month, unless the contract allows it (s 13(5)).
  • Check the work was last carried out within 12 months, or within the longer contract period (s 13(4)).
  • Identify the work against the contract's payment schedule structure, with supporting detail attached (s 13(2)(a)).
  • State the claimed amount (s 13(2)(b)).
  • Put the “made under the Act” statement on the face of the claim (s 13(2)(c)).
  • Head contracts: attach the supporting statement in the approved form (s 13(7)).
  • Serve on the person liable to pay, by every contractually permitted method, and keep the transmission record.
  • Diarise the respondent's schedule deadline from the actual service date, counting business days under s 4.

When to get advice

Get advice before serving if it is unclear whether the arrangement is a construction contract or falls within an exclusion such as s 7(2)(c), whether the contract was entered into before or after 21 October 2019, or whether a further claim can be served in a month that already has one. Get it as soon as a respondent says a claim is invalid.

Sources

  1. 1Building and Construction Industry Security of Payment Act 1999 (NSW) ss 4(1), 7, 8(1), 13, 14(4), 15, 31, sch 2 cl 6Current version from 20 August 2024. Schedule 1 of the Fair Trading and Building Legislation Amendment Act 2026 (NSW) had not commenced at 14 October 2026.
  2. 2Fair Trading and Building Legislation Amendment Act 2026 (NSW) s 2, sch 1Schedule 1 commences on proclamation; not commenced at 14 October 2026.
  3. 3Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391
  4. 4Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161
  5. 5TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93
  6. 6Kwik Flo Pty Ltd v SE Ware Street Dev Pty Ltd [2026] NSWCA 9
  7. 7Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52

Malachy Mullin BSc (Hons) MRICS ACIArb

Chartered Quantity Surveyor and Director of SUMIT, a firm regulated by RICS.

0452 549 257malachy@sumitconsulting.com.auExpert CV

Related service: Security of payment

This article is general information about the law as at the last reviewed date. It is not legal advice, and it is not advice on your contract. For advice on a specific contract or dispute, speak to your lawyers. SUMIT provides commercial and claims advice; it does not provide legal advice.

Insights by emailFree

Practical notes on contracts, claims and payment law

New case notes and guidance on security of payment, claims, variations and contract administration in Australian construction, in one email, no more than once a month. Written for contractors, subcontractors, principals and their lawyers.

Written by Malachy Mullin MRICS ACIArb, Director of SUMIT.

Tell us more (optional)

No more than one Insights email a month. Every email has an unsubscribe link. Your details are handled as our privacy policy explains.